Routine repairs such as painting, plastering and tiling generally need no BMC permission, but societies usually want written approval first. Changes to walls, beams or columns need BMC approval, with an architect's drawings and a society NOC. Rules change, so confirm with your society and the BMC before work starts.

A note on sources

The sources we found for this topic are mostly property portals, news reports and lawyer Q&A pages, not the current BMC rulebook. Treat this guide as a way to ask the right questions, and check the current rules with the BMC, your society and a lawyer before you start.

What you can usually do without BMC permission

Under section 342 of the BMC Act, 1988, routine tenantable repairs such as plastering, painting and pointing can be done without BMC permission. A BMC guideline summary reported by Housing.com also lists internal work such as tiling, modular kitchens and bathroom upgrades as allowed without permission from the BMC.

Two conditions apply. The flat's original structure must be legal and match the approved building plan, and changes should be supervised by a registered architect or structural engineer.

What needs approval

Changes to load-bearing walls, beams or columns need BMC approval. Guidance we found says that removing an internal wall in an approved building needs municipal permission, supported by a registered architect's drawing and an NOC from the society. Bigger changes may need amended plans, and smaller ones may need only an intimation to the BMC. Which applies to your flat depends on the work, so ask your architect.

Why the society NOC comes first

Most guides agree that no renovation work should start without a written NOC from your cooperative housing society, and that the society must issue it before the BMC will look at a larger application. Many societies also ask for a renovation letter that describes the scope of work, the dates, the noise and how debris will be handled.

  • Ask the society for its renovation rules, working hours, lift and material-handling rules and any deposit.
  • Describe the work in writing, with dates and the names of the contractor and architect.
  • Keep the signed NOC with you on site.

A sensible order of steps

  1. Get the approved plan of your flat and building.
  2. Decide what you want to change, and whether it touches walls, beams, columns, plumbing stacks or the external face.
  3. Get a structural opinion before you draw a change that affects walls or openings.
  4. Have an architect prepare drawings and a clear scope of work.
  5. Apply to your society for a written NOC.
  6. Take whatever BMC intimation or approval your architect advises.
  7. Only then appoint the contractor and start work.

How we approach a structural change

We begin with the structure, not the design. On Tyndall, a retrofit of two stacked apartments, the first step was a structural audit and close coordination with engineers, because the building used a load-bearing system and walls could not simply be knocked down. We came to a plan that worked with the structure, not against it.

Royal Impression joined two compact apartments into one home. Joining flats raises questions about structure, services and approvals, which is why we advise checking them before you commit.

Our studio is in Pune. If your flat is in Mumbai, we would first discuss how site visits and approvals would work. Our guide to renovate or rebuild an old house covers the decision for houses, and you can get in touch with your floor plan.

Common questions

Do I need BMC permission to renovate my flat in Mumbai?
Routine repairs and internal finishing work generally do not, according to the guidance we found. Structural changes do. Confirm what applies to your work with the BMC and a registered architect.
Can I remove an internal wall in my Mumbai flat?
Only after checking it is not load-bearing and getting the permissions your architect advises, including a society NOC. Do not start work before you have both.
Is a society NOC compulsory for renovation?
Most guides say yes: no renovation work should begin without a written NOC from your society. Check your own society's bylaws.
Can two flats be joined into one in Mumbai?
Sometimes. It depends on the structure, the services, your society's consent and the approvals required. Get a structural opinion and legal advice before you buy or start work.